Analisa Pengaruh Tingkat Penerapan BIM 5D Terhadap Kinerja Waktu Proyek Konstruksi
DOI:
https://doi.org/10.31599/s1vpbf30Keywords:
BIM, BIM5D, Time, PerformanceAbstract
In construction, risks are usually requests for additional time, cost, or quality of work. Disputes will
occur If risks are not resolved properly. In the industrial revolution 4.0, we can use the Building
Information Modeling (BIM) method to increase efficiency. BIM is a digital display that contains all
information about building elements integrated with the building's life cycle period. BIM will optimize
the performance of construction projects. In Indonesia, several consultants/contractors have
implemented BIM in construction projects. This study aims to determine and analyze what factors in the
process of implementing BIM 5D that affect the performance of construction project time. The research
method used is descriptive research method with the Q-method approach using closed survey research
instruments to 53 contractor/consultant respondents using BIM. The results obtained from the 5D BIM
indicators have 3 effects on the time performance of construction projects.